How Long Does Kitchen Remodeling Take? Timelines and What to Expect

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in Coral Gables

Last updated November 17, 2026

A small remodeled galley kitchen with cabinets to the ceiling
A walk-in pantry with wood shelving
A remodeled kitchen with a waterfall island and wood cabinets
An open kitchen and dining area after a remodel
A galley kitchen opened up to the dining room with a new peninsula
A wide opening with a new beam where the kitchen wall was removed
A remodeled hall bathroom with subway tile and a floating vanity
A remodeled primary suite with built-in wardrobes and a window seat
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate

How Long Does Kitchen Remodeling Take? Timelines and What to Expect

Most kitchen remodels in South Florida run four to six weeks longer than the original quote, and the reason is almost never the work itself. It’s that nobody pulled the permit before ordering the cabinets. We’ve walked into Coral Gables kitchens where the homeowner had been quoted “six weeks, start to finish,” only to watch the permit sit in the Miami-Dade queue for three weeks while the cabinet order wasn’t even placed yet. This guide breaks the remodel down by actual trade days rather than the optimistic calendar weeks contractors quote to win the job, so you can read a schedule for what it really is. It covers Coral Gables-specific permit timing, why cabinet lead time drives the whole calendar, and how to spot a padded timeline before you sign.

Call (833) 510-5367

Quick Answer

A typical kitchen remodel takes 8 to 12 weeks of trade work plus whatever the permit queue and cabinet lead time add, which in Miami-Dade commonly pushes the realistic total to 14 to 20 weeks from signed contract to final walkthrough. The work itself rarely runs long – the biggest variable is the gap between permit approval and cabinet delivery.

Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence

Table of Contents

Phase-by-Phase Breakdown by Trade Days

Calendar weeks hide a lot. What actually matters is trade days – the days each trade is on-site working, and the gaps between them. Here’s where the time really goes during a standard Coral Gables kitchen remodel, based on the timelines we typically write into a project schedule.

  1. Demolition: 2 to 4 days. Tearing out cabinets, countertops, flooring, and sometimes a partition wall. If plumbing fixtures are moving or a wall comes down, add a day for careful separation of what’s salvageable from what goes to the dumpster.
  2. Rough-in (plumbing and electrical): 3 to 5 days. “Rough-in” is the trade’s word for running pipes and wiring through open walls before anything gets closed up. Moving a sink changes the drain line. Adding a range hood changes the electrical. Every fixture shift lengthens this phase.
  3. Inspection hold: 1 to 10 days. The rough-in has to be inspected before drywall goes up. In Coral Gables, the wait for an inspection slot can run a few business days to more than a week, and it isn’t something any contractor can compress. This is the phase most quote sheets silently cut out.
  4. Drywall, patch, and paint: 3 to 5 days. Hang, tape, mud, sand, prime. Dry time between coats depends on South Florida humidity, which is why this phase can stretch in summer.
  5. Cabinet install: 2 to 4 days. Set the boxes, level them, install uppers and crown, hang doors and drawers. Custom configurations take longer than stock. KraftMaid and Wellborn lines have published delivery windows, and the install team should have the exact cabinet height and wall plumb confirmed before the truck arrives.
  6. Countertop template and fabricate: 5 to 10 days. Cambria and Caesarstone slabs are templated after the base cabinets are set, not before. This template-to-install gap alone is a full work week on most schedules.
  7. Counter install, backsplash, plumbing trim, electrical trim: 3 to 5 days. Sinks and faucets get hooked back up, outlets and light fixtures get trimmed out, and the tile backsplash gets set and grouted.
  8. Final punch list and inspection: 2 to 5 days. Final inspection, touch-up, and the walkthrough where the contractor and homeowner list anything that needs correction.

Add those trade days up and you get 23 to 43 working days, which is roughly 5 to 9 calendar weeks of trade work. Add permit and cabinet lead time and the realistic Coral Gables total lands in the 14 to 20 week range for most jobs.

How Miami-Dade Permit Timelines Add Real Buffer

Miami-Dade County permit review for a kitchen remodel typically takes two to four weeks for a standard scope, and longer when the plan involves structural changes, moving a gas line, or a new exterior opening. That’s the permit window. Add in the time to prepare the application and gather drawings and you’re at roughly four to six weeks of dead time before a single hammer swings.

The honest problem is that many written quotes start the clock on the wrong event. A quote that says “six weeks from contract” is really saying “six weeks from the day we’re allowed to start,” and the homeowner reads it as six weeks from today. We see this play out across Coral Gables whenever a homeowner has a hard deadline – a holiday, a family visit, a sale closing – and discovers the permit wasn’t submitted until after the deposit cleared.

What buffer actually looks like in a written schedule:

  • Permit application submission listed by date, not by “weeks from contract.”
  • Expected review window as a range of weeks, with a note about what could stretch it (structural, gas, plan changes).
  • Cabinet order placed concurrent with permit submission, not after approval – so the two clocks run in parallel rather than one after the other.
  • Rough-in inspection hold on the schedule as a line item, not absorbed invisibly into the “framing” or “drywall” phase.

For a fuller picture of what a permitted scope includes in this market, see our page on general contracting in Coral Gables.

Why Cabinet Lead Time Is the Longest Variable

Most delays that turn into real schedule blowouts aren’t labor. They’re cabinets. A semi-custom cabinet line with published delivery windows typically runs six to ten weeks from order release to delivery, and custom runs longer. If the contractor orders cabinets after permit approval – which is the standard sequence at most shops – the six-week cabinet lead stacks on top of the three-to-four-week permit wait, giving you a two-and-a-half month runway before demo even makes sense.

Some framings of this industry say “order cabinets at contract signing.” That’s the right instinct but the wrong execution if the plan hasn’t been finalized. A cabinet ordered before the layout is fully locked in with the homeowner – confirmed wall dimensions, appliance sizes, sink placement – risks a change order after the boxes are milled. The disciplined sequence is: finalize the layout, order the cabinets, submit the permit, all within the same two-week window at the front of the project.

How to verify cabinet lead time before you sign:

  • Ask for the specific cabinet line and finish by name. KraftMaid, Wellborn, and similar lines publish approximate lead times on their dealer portals.
  • Request the date the order will be placed and the date the truck is expected. Two dates, not “in a few weeks.”
  • Ask what happens if the cabinet arrives damaged or short. A real schedule includes a re-order buffer for a door or drawer that arrives chipped.
  • Confirm the fabricator timeline for Cambria or Caesarstone slabs runs from the date of template, not the date of order.

The install team should meet the homeowner and confirm the actual cabinet list against the approved layout at least two weeks before delivery. A cabinet arrived with no wall to sit against is a signature of a schedule that was never really a schedule.

What a Written Subcontractor Schedule Looks Like

A subcontractor schedule is the sheet that lists, by trade, which crew is on-site and on what days. In a disciplined remodel it’s not a soft target – it’s a page in the project packet that the homeowner can hold next to the written price. Here’s what it should show for a Coral Gables kitchen:

  1. Trade names and lead days. Plumber, electrician, drywall crew, painter, cabinet installer, countertop fabricator, tile setter, final trim. Each with a start and finish date, not a range of weeks.
  2. Hand-off points. The exact day the plumber and electrician clear rough-in so the inspector can be called. The exact day the drywall is finished enough for cabinets to be staged.
  3. Lock-in language. “Subcontractor committed for [start date]” or “confirmed for [week].” A verbal “they’ll be there” is not lock-in – the sub isn’t scheduled, the phone call just happened.
  4. Consequence clauses. What happens if a sub misses a scheduled day. What happens if a change order moves the schedule. Any serious schedule has that clause, and a serious homeowner should ask for it.
  5. Buffer line items. Where the pad is. A schedule with zero buffer between trades is a schedule that eats its own contingency on the first missed day.

This is where most remodeling companies lose the schedule. When trade crews are locked in with a written commitment and reconfirmed 48 hours ahead of their start date, the whole calendar holds. When the only record is a texted “I’ll see you next week,” one missed day cascades into the cabinet install, the countertop template, the final inspection, and the walkthrough date.

How to Read a Project Schedule Before You Sign

A schedule is the cheapest thing you can review before you sign a kitchen contract. Read it the way you’d read a price sheet. Here’s a short list to check line by line.

  1. Does it start from permit submission or permit approval? “Week 1” should be a real calendar date, not “the week we get going.”
  2. Is the permit hold shown separately from the trade days? If the whole permit window is buried in a “pre-construction” phase, you can’t see what that phase is really costing you.
  3. Are cabinet order date and delivery date both on the schedule? Both. In writing.
  4. Is the rough-in inspection hold a line item? If it’s not, your contractor is either skipping the inspection or hiding the wait.
  5. Are the finish phases sequenced logically? Countertop template comes after cabinet install, not before. Backsplash comes after counters. Trim plumbing comes last. A schedule with these out of sequence is a schedule written to look pretty.
  6. Is there a buffer between trades? A kitchen built on back-to-back trade days with no slack is not a faster kitchen – it’s a kitchen that will miss its date by a week if any sub is one day late.

A padded schedule usually shows up in the finishes. If the paint crew is booked for seven days on a single-room repaint, or the final punch list is listed as two weeks, the extra time is either padding or a real problem. An unrealistic schedule usually shows up at the front – one week for demo, one for rough-in, one for drywall, and no permit hold at all. Neither is the schedule you want to sign. You want the one that matches the trade reality documented above.

For a deeper look at the finish sequence on a full kitchen, see our page on kitchen remodeling in Coral Gables.

Coral Gables-Specific Timing Factors

Coral Gables kitchens have a few timing quirks that don’t show up in a Miami-Dade County permit timeline or a contractor’s generic schedule. The city’s historic districts – Coral Gables has them and the review process can add weeks – mean any exterior-facing change (a window, a door, an exterior finish alteration) may need historic preservation review on top of the standard permit. Inside an interior kitchen remodel that’s usually not an issue, but a kitchen that opens to a new rear patio door is in different territory.

South Florida humidity affects every finish phase. Cabinets need to acclimatize before install – the boxes should sit inside the conditioned house for 24 to 48 hours before they’re hung, or the doors can warp in the first summer. Drywall mud and paint dry slower in summer than winter, so a schedule that assumes winter dry times will slip when it hits a July install. Flooring – wood, luxury vinyl, tile – has its own acclimation window, and a tile set over a substrate that hasn’t been given a full cure can crack within the first year.

Older Coral Gables homes bring their own variables. A 1940s kitchen that hasn’t been touched since the 1980s may turn up cast iron drain lines that need replacement, knob-and-tube wiring that has to be brought up to code, or a wall that doesn’t sit plumb because the house has settled three-quarters of an inch over eight decades. In Coral Gables we budget an extra three to five trade days on any pre-1970 home for what the walls turn up once demo is done. If a contractor has quoted the same duration for a 2020 townhome and a 1955 Mediterranean Revival, the quote is a guess.

For the plumbing side of that equation, our page on bathroom remodeling in Coral Gables covers how adjacent wet-wall work affects shared timing when a kitchen and bathroom are on the same schedule.

How Timeline Length Affects Cost in Coral Gables

Timeline and cost are linked at the seams. Longer schedules don’t automatically cost more – but specific delays do, and knowing which ones is how you read a price realistically.

  • Permit delays add carrying costs, not construction costs. Rent, storage, a rental kitchen, and any hold on adjacent rooms all run while the permit is in review. In Coral Gables that typically shows up as $1,500 to $3,500 in soft cost over a four-week permit hold on a full kitchen.
  • Cabinet lead time adds nothing if it runs parallel to the permit. This is the single biggest cost-saving schedule move in a kitchen remodel. Two clocks in parallel, not two in series.
  • Change orders add cost two ways. The change itself and the days it pushes the following trades. Changing a sink location after rough-in is a four-figure change order on a typical Coral Gables kitchen because it hits plumber, drywall, tile, and counter fabricator all in one shot.
  • Realistic Coral Gables kitchen remodel pricing (labor and materials, mid-range finishes): $65,000 to $95,000 for a full gut with semi-custom cabinets and stone counters. Higher for historic homes with substantial electrical or plumbing replacement. Lower for a refresh that leaves the layout intact.
  • A written price beats a low price. A quote you can’t measure against the scope is a quote that will move. Our written price – itemized line by line, no change orders except on signed change orders – is not a budget number, it’s the number.

Every Bradford Remodeling kitchen carries the 365-Day Done Right Promise: if the work fails in the first year, we come back and correct it at no charge, and that promise is in writing before a single tool comes out. That’s the framework behind The Garrison Standard – everything measurable and nothing verbal.

Common Mistakes to Avoid

  • Accepting “weeks from contract” as a start date. Ask for the permit submission date and the expected review window, printed in the schedule. A quote that doesn’t name those isn’t a schedule.
  • Ordering cabinets after permit approval. That serializes two timelines that should run in parallel and typically adds four to six weeks to the total. In Coral Gables this is the single most common cause of a blown deadline.
  • Signing a schedule with no subcontractor lock-in. “They’ll be there” is not a scheduled trade. A written plan should name each sub and confirm their start week.
  • Skipping the rough-in inspection hold. Some contractors quote around the inspection to hit a shorter number. That’s a compliance problem and a safety problem, and it doesn’t survive the final inspection anyway.
  • Ignoring acclimation for South Florida. Cabinets, wood flooring, and tile all need time to settle into the house’s climate. In Coral Gables that’s usually one to three days depending on material and season, and a schedule that doesn’t allow for it risks a first-year failure.
  • Treating a Coral Gables historic property like a new build. Pre-1970 homes can turn up cast iron, knob-and-tube, or an out-of-plumb wall. Budget three to five extra trade days for demo-day discoveries.
  • Comparing schedules on total weeks only. Two 14-week schedules can be wildly different. One shows 12 weeks of trade days plus 2 of buffer, the other shows 8 weeks of trade days padded with 6 weeks of padding. Read the phases, not the total.
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

When to Call a Professional

Any kitchen remodel that touches plumbing, electrical, or a load-bearing wall needs a licensed trades team and a permitted scope. Beyond the code requirements, a few scenarios call for a real conversation before anyone picks up a sledgehammer: a Coral Gables home built before 1970 where you don’t know if the wiring has been updated; a layout change that moves the sink or range; a kitchen that opens to an exterior wall in a historic district; or a project where the design is done and you’re ready to lock in a schedule and a written price. Bradford Remodeling Co Coral Gables offers free estimates in Coral Gables – call (833) 510-5367. We’ll bring the schedule, the permit timeline, and the written price to the first visit, not the fifth. Every completed project gets The Garrison Standard in writing and the 365-Day Done Right Promise attached.

Frequently Asked Questions

Installers leveling a new base cabinet during a kitchen remodel

The Bottom Line

The timeline of a kitchen remodel is set before demo day. It’s set by the permit queue, the cabinet lead time, and whether the contractor locked in the subcontractor schedule in writing – in that order. A realistic Coral Gables kitchen runs 14 to 20 weeks from signed contract, with most of that being permit and cabinet time that a disciplined schedule runs in parallel. Read every quote for the permit submission date, the cabinet order and delivery dates, the rough-in inspection hold, and the named subs with confirmed weeks. If those four things are in writing, the number you’re reading is real. If they’re not, the quote is a guess. For a schedule and a written price before a single tool comes out, see our Bradford Remodeling Co Coral Gables home page or call (833) 510-5367 for a free estimate.

Written by the team at Bradford Remodeling Co Coral Gables.

Getting started with Bradford in Coral Gables

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead measuring a kitchen with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A remodeling crew arriving at a home with lumber and tools

Your Coral Gables team

A local vetted partner works across Coral Gables and the towns around it, to the same written standard as every Bradford job.

Areas we serve
A worker laying floor protection and a dust barrier before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in Coral Gables? Licensed & insured · free written estimates
Call (833) 510-5367
Local Service Coverage

Request a Free Estimate in Coral Gables

Tell us what you need - Bradford Remodeling Co Coral Gables responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Prefer to text? Text Us
Call Now - 24/7 Dispatch